DEDICATED PRESSURE SYSTEMS LTD.

Telephone 01372 803 675
Fax 01372 803 678
Email dps@heatweb.com
 
Internet http://www.heatweb.com

The Institute of Plumbing

R/O Shops, 9-19 Manor Green Road, Epsom, Surrey KT19 8RA
  

Installation Instructions
High Performance UFH Heat Bank Thermal Store

3109-1  30/01/01

Heat Bank Thermal Store System  
Xcel unit for connection to remote F+E  
Twin heat exchangers (45 ltr/min)  
Directly heated from remote source  
40mm Foam Insulation  
GX-Plan primary controls  
Underfloor Primaries  
Danfoss VMV20 UF Control Valve  
Fitted Primary Pump, Alpha 6m  
All fitted controls are wired  
Thermostatic Blending Valve 1''  
Backup Immersion Heater  
Flow Switch By-Pass  
Cased  


2   Plate Heat Exchanger
3   Heat Exchanger Pump
4   Flow Switch
5   Thermostatic Blending Valve, Aquamix 1"
6   Manual Air Vent
8   Vent
11  Y-Pattern Strainer (supplied loose)
13  Cold Feed / Expansion
14  Immersion Heater 3kW Incaloy with Stat
16  Cold Mains In, 22mm
17  Hot Mains Out, 22mm
18  Drain Cock
19  Flow From Boiler
20  Return to Boiler
23  Flow to Heating Circuit
24  Return from Heating Circuit
26  Primary Pump - Grundfos Alpha 6m
27  Boiler Pump UPS 15/50
38  Cylinder Immersion Thermostat
41  Primary Blending Valve
42  Wiring Centre
76  Danfoss VMV20 Valve with RAVK Sensor

 

Unit ID

XC-275-3109-1

Capacity

275

Base Diameter

500

Overall Diameter

580

Height

1700

Contents:
1. Introduction
2. General Requirements
3. Mains Water Supply
4. Connections:
5. Wiring
6. Filling
7. Commissioning
8. Fault Finding
9. Servicing
10. Spares
11. User Instructions